  1. June 2024

    ASCEND study results published

    Thales Alenia Space announces results of ASCEND, a European Commission-funded feasibility study on space data centers. It finds that a real cut in emissions would need a launcher about ten times less emissive over its life cycle, and sets an aim of one gigawatt deployed before 2050.

    Source: Thales Alenia Space ↗

  2. September 2024

    Starcloud (then Lumen Orbit) publishes its white paper

    "Why we should train AI in space" sets out the startup's case for gigawatt-scale data centers in orbit. The company was renamed Starcloud in 2025.

    Source: Starcloud ↗

  3. February–March 2025

    Lonestar's data center payload reaches the Moon

    Lonestar's small Freedom data center (an 8 TB SSD and an FPGA) launched on 26 February 2025 aboard Intuitive Machines' Athena lander. Athena touched down but fell on its side; Lonestar says the payload ran tests en route, in lunar orbit and briefly on the surface.

    Source: DCD ↗

  4. November 2025

    Google announces Project Suncatcher; Starcloud-1 launches

    Google unveils Project Suncatcher, a moonshot to put its AI chips on solar-powered satellites. The same month, Starcloud launches a satellite carrying an NVIDIA H100 GPU.

    Source: CNBC ↗

  5. December 2025

    First AI model trained in space

    Starcloud reports training NanoGPT on the H100 in orbit and running Google's open Gemma model on its Starcloud-1 satellite.

    Source: CNBC ↗

  6. 11 January 2026

    Kepler's first optical relay tranche launches with Axiom nodes

    Ten Kepler satellites with multi-GPU compute modules launch on a Falcon 9. They carry Axiom Space's first two orbital data center nodes.

    Source: Kepler Communications ↗

  7. January 2026

    Penn Engineering presents a tether-based design

    Researchers describe a largely passive, tether-linked chain of computing nodes that could host thousands of nodes and up to 20 megawatts of computing in simulation.

    Source: Penn Engineering ↗

  8. January 2026

    SpaceX files for a million-satellite constellation

    SpaceX asks the FCC to approve a constellation of up to one million satellites intended to work as an orbital data center.

    Source: SpaceNews ↗

  9. February 2026

    Starcloud asks the FCC for up to 88,000 satellites

    Days after SpaceX's filing, Starcloud submits its own proposal for an orbital data center constellation of up to 88,000 satellites.

    Source: PCMag ↗

  10. March 2026

    Kepler switches on computing across its constellation

    Kepler commissions distributed on-orbit computing on all 10 Tranche 1 satellites, using 40 NVIDIA Jetson Orin modules.

    Source: Kepler Communications ↗

  11. April 2026

    Orbital sets its first test mission for 2027

    Orbital says Orbital-1 is scheduled to launch on a Falcon 9 in April 2027 to test GPU operation and radiation hardening in orbit.

    Source: Orbital ↗

  12. May 2026

    ESA study contract for Edge Aerospace

    Under ESA's Space Cloud program, Luxembourg-based Edge Aerospace is to study the commercial viability, architecture and a use-case roadmap for orbital data centers.

    Source: Payload ↗

  13. July 2026

    Groups ask the FCC to pause applications

    Environmental and scientific groups petition the FCC to pause orbital data center licensing pending an environmental review.

    Source: SpaceNews ↗

  14. November 2026

    FCC approves SpaceX's orbital data center plan

    The FCC authorizes SpaceX to deploy up to 1 million orbital data center satellites, over petitions to deny from Amazon's Kuiper Systems, Viasat and the American Astronomical Society.

    Source: CNBC ↗

  15. Planned: Q1 2029

    Project Suncatcher heavy-lift launch (target)

    Google's target for a New Glenn launch of Suncatcher satellites into sun-synchronous orbit.

    Source: Google ↗